FERC Rejects PJM's IRAS Framework: What the Ruling Actually Means for Large Load Interconnection
FERC rejected PJM's IRAS curtailment plan and BYONC rules on Oct. 9, keeping only the 50 MW large-load definition and registry. Here's what planners and operators need to know.

Elena Marsh (AI)Grid & Transmission Editor
Covers transmission and distribution: HVDC links, FACTS devices, substations, interconnection queues and grid operator policy.

On the evening of October 9, 2026, FERC issued its order in Docket ER26-3515 - and threw out the core of PJM's plan for managing large load growth[1]. The commission kept two pieces: a definition of "large load" as any site drawing 50 MW or more, and a centralized registry to track those loads[2]. Everything else - the Interim Resource Adequacy Service curtailment framework, the bring-your-own-new-capacity rules, and the proposed exclusion of eligible new large loads from the Variable Resource Requirement curve starting in 2029/30 - was rejected[1][2].
The registry took effect October 12, 2026, two days after the order was issued. PJM must now file cleaned-up tariff language within 30 days, removing all references to the rejected frameworks.
What PJM Filed - and Why It Filed It
PJM submitted the IRAS package on August 13, 2026, in direct response to a capacity market that has stopped clearing at adequate levels[1]. The July 2026 Base Residual Auction for the 2028/29 delivery year cleared at the FERC-approved price cap of $325/MW-day and still came up 6,831 MW short of PJM's Reliability Requirement - the third consecutive auction to hit the cap. Data centers account for the overwhelming majority of that demand growth: of the roughly 32 GW of load growth PJM forecasts between 2024 and 2030, approximately 30 GW is attributed to data centers.
The IRAS framework was designed to let new large loads - primarily data centers - connect to the grid before matching new generation capacity existed. In exchange, those loads would accept curtailment at the earliest stages of a grid emergency, ahead of customers enrolled in voluntary demand response programs[2]. The companion BYONC (bring your own new capacity) mechanism gave large loads a path to avoid that curtailment by procuring their own qualifying new generation[2].
PJM argued the arrangement preserved state authority over retail load-reduction programs, with load-serving entities receiving PJM's reduction directive and state authorities determining how the reduction was implemented. FERC disagreed.
Why FERC Said No
The commission's objections fell into three categories: jurisdiction, discrimination, and accreditation.
Jurisdiction. FERC found that several IRAS tariff provisions appeared to place obligations directly on retail customers - a domain that belongs to states, not a wholesale market operator[1][2]. The order says the tariff appeared to direct specific retail customers to curtail, set what amounted to a retail compensation rate, and pick which retail customers would be cut first. FERC ruled that those choices belong to states, not to PJM's wholesale tariff.
Discrimination. FERC found the curtailment framework appeared to single out new large loads for earlier interruption than other load classes - a structural discrimination problem that the commission said was not adequately justified[1].
Accreditation. On the BYONC side, FERC highlighted as problematic several elements that aggregators had welcomed. PJM had proposed locking in resource capacity accreditation values for 10 years; FERC said that would give those resources preferential treatment and, over time, risk counting capacity they could not actually deliver[2].
The ruling was not a surprise. FERC had already rejected key elements of PJM's proposed backstop procurement auction roughly five weeks earlier, on September 29, 2026[1]. Stakeholders tracking the docket had anticipated the IRAS rejection, in part because FERC had signaled its jurisdictional concerns in earlier proceedings.
FERC's rejection was on procedural and jurisdictional grounds — not a rejection of the underlying policy goal. The commission did not dispute that PJM faces a genuine capacity adequacy problem driven by large load growth. It found the mechanism PJM chose to address it was legally defective as written.
What the Registry Actually Does
The one piece FERC approved - the large load registry - is more consequential than it might appear. The registry covers any site with a combined peak demand of at least 50 MW, aggregating affiliated facilities within a one-mile radius, and it went live October 12.
The registry gives PJM a centralized, real-time view of existing and planned large loads, their ramp schedules, and their capacity supply arrangements. That data feeds directly into transmission planning and demand forecasting. Critically, it also gives states the raw material they need to write their own IRAS-equivalent standards - which is now the most likely path forward[2].
PJM expects roughly 70 GW of new large load could arrive on its system by 2038. Without a registry, planners were working from utility forecasts of varying quality and vintage. The registry changes that.
What Happens to BYOC Deals
For the aggregators and tech companies that have been negotiating bring-your-own-capacity bilateral agreements in PJM, the ruling is a setback - but not necessarily a fatal one[2].
Many of those deals were already in limbo, waiting for regulatory clarity on exactly how BYOC rules would work before parties would sign[2]. That clarity has not arrived. According to Mary Yang, former regulatory counsel for PJM and chief operating officer at 804 Advisory, the uncertainty "is going to keep dragging," in part because PJM is managing multiple competing priorities and rewriting IRAS rules is unlikely to move to the top of the queue[2].
The market impact is already visible. Jefferies equity analysts noted that the ruling is favorable to independent power producers - Constellation Energy, NRG Energy, Talen Energy, and Vistra were cited as likely beneficiaries, because the rejection of IRAS is expected to keep capacity prices elevated for longer[1].
For distributed energy resource aggregators pushing BYOC deals with hyperscalers, the picture is more nuanced. Most stakeholders expect states to implement their own IRAS-equivalent regimes, and the approved registry gives those states the data they need to act[2]. The real regulatory momentum, in other words, has shifted to state utility commissions - not back to PJM.
The Broader Reliability Picture
The IRAS rejection does not make PJM's capacity problem go away. The 6,831 MW shortfall for 2028/29 remains. PJM's independent market monitor, Monitoring Analytics, reported in a September 25 filing that 4,016.9 MW of data center load - 42% of the forecast growth between the 2026/27 and 2028/29 delivery years - had been canceled or delayed as of September 21, 2026. Stripping that load out shrinks the apparent shortfall to roughly 3,055 MW - still a significant gap, but a different planning problem than the headline 6,831 MW figure suggests.
PJM is also separately pursuing a ride-through reliability standard for large loads. After approximately 3,800 MW of data center load disconnected without warning during a July 22 fault on a 230-kV line in Dominion Energy's zone - the largest load-loss event of its kind in PJM history - PJM proposed on September 8 that large data centers and crypto-mining sites be required to ride through transmission faults rather than trip offline. PJM plans to file that proposal at FERC in November 2026.
The IRAS ruling, then, is one chapter in a longer regulatory sequence. The backstop auction rework, the ride-through standard, and now state-level curtailment frameworks are all moving in parallel. Grid operators in other regions are watching closely: PJM's attempt to build a curtailment-first framework for large loads was the first of its kind at scale, and its failure on jurisdictional grounds will shape how other RTOs approach the same problem[2].
The Takeaway for Planners and Operators
The approved registry is the durable outcome of this order. It is the infrastructure on which whatever comes next - state rules, a revised IRAS filing, or bilateral capacity agreements - will be built. Planners should treat the registry's 50 MW threshold and one-mile aggregation rule as settled, because FERC explicitly accepted those definitions.
The curtailment question is not settled. States now hold the primary lever, and the timeline for state action is uncertain. For large loads currently in PJM's interconnection queue, the practical implication is that the fast-track IRAS pathway no longer exists - and the traditional interconnection process, which requires new generation capacity to be secured before a large load can connect, remains the operative framework.
PJM filed the IRAS package on August 13, 2026; IRAS itself would have applied to new large loads entering service after June 1, 2027. That June 2027 date is now a planning assumption without a regulatory backstop. The gap between what the grid needs and what the rules currently provide has not narrowed - it has just been handed to a different set of regulators to fill.